Gochang Demonstration Complex Full Digital Substation Construction Project
Project Overview
DIVISION | DETAIL | |
---|---|---|
CONSTRUCTION PERIOD | WORK SCHEDULE | 2023.11.06 |
FIELD WORK AND PROGRESS SCHEDULE | 2023.11.06 ~ 2023.12.22 | |
COMPLETION PROCESSING | 2023.12.21 | |
CURRENT STATUS OF FIELD PERSONNEL | 1 site construction and safety manager, 1 person for drawing work, 6 people for site construction and installation, 3 people for remodeling work | |
CONSTRUCTION WORK SCOPE | Remodeling of already delivered panels and supply of new panels (including installation and cable laying) | |
¡á Panel remodeling for delivery
- 154kV BUSBAR PROTECTION RELAY PANEL - 154kV TRANSMISSION LINE PROTECTION RELAY PANEL - 154kV M.TR PROTECTION CONTROL PANEL - 154kV M.TR CONTROL AND SURVEILLANCE PANEL - 154kV BAY CONTROL PANEL - 23kV BAY CONTROL PANEL - SA LINKED EQUIPMENT PANEL - TEST EQUIPMENT GROUP - 154kV TRANSMISSION LINE PROTECTION RELAY PANEL(West Gochang side) |
||
¡á New panel supply
- 154kV SUBSTATION AUTOMATION OPERATING SYSTEM - Station/Process bus NETWORK TOPOLOGY REPLACEMENT PANEL - 154kV #1 TRANSMISSION LINE PROTECTION RELAY PANEL - 154kV #2 TRANSMISSION LINE PROTECTION RELAY PANEL - 154kV BUSBAR PROTECTION RELAY PANEL - 154kV #1 TRANSFORMER PROTECTION PANEL - 154kV #2 TRANSFORMER PROTECTION PANEL - 154kV TRANSFORMER CONTROL PANEL - 154kV SUBSTATION INTEGRATED CONTROL PANEL IED PANEL - 23kV #1 BUSBAR PROTECTION RELAY PANEL - 23kV #2 BUSBAR PROTECTION RELAY PANEL - 23kV CENTRALIZED PROTECTION PANEL - MONITORING SYSTEM |